1. Are back out procedures
in place? Do we have appropriate, pre-tested, recovery procedures ready?
2. Do all units have the necessary
training and documentation to support the change?
3. If appropriate, does the
Support Center have the proper training, documentation to support the change?
4. If appropriate, does the
Help Desk have the needed training and/or documentation to
support the change?
5. Do we know exactly when
the change will be implemented, and has that been
communicated to users?
6. In regards to new server
installations: Have all unnecessary software been removed and unneeded services
turned off? Applicable patches applied?
7. Does a security scan show
NO medium or high-risk vulnerabilities?
8. Has the change been scheduled
to minimize the user impact, in relation to the cost?
Is the scheduled time the best time for the change, is it scheduled in the established
change window? Have we scheduled with the user in mind, rather than for staff
convenience?
9. Have the users been properly
notified, with adequate lead-time, are banners necessary and posted? (A discussion
on how the users have been notified may be relevant) Have users, who operate
as "clients" to central systems, rather than "login" users,
been notified? The Help Desk, the CSC, and the Publications group offer to participate
in relevant user notifications. If you need assistance from these areas, ask.
10. Have users been trained,
provided with documentation, or otherwise informed of anything different than
they need to be aware of or to do? (From a user point of view, what is the result
or impact of this change?)
11. Has the change been communicated
to all appropriate areas within UITS with adequate lead-time?
12. Are all other appropriate
UITS areas ok with implementing the change?
13. Will we know if the change
is a success? Will we know if the change was not a success? If not a success,
are measures in place for appropriate action, and additional user notification
as required?
14. Do we know whom the person
is who is overall responsible for implementing this change?
15. Do staff members and users
know whom to contact if there are further questions, either before or after
the implementation?
16. Have you informed your
manager, sent them a copy of the SCR, do they know of the change and approve?
17. As a general rule, if the
answer to any question is NO, then the change should not be implemented until
all questions result in a YES answer.